Featured Projects

2014 - Amber Trails Phase 16 Roadworks

Owner: Genstar Developments | Value: 1.0 Million | Consultant: Stantec Consulting Ltd.

The roadworks package in Amber Trails involved all the aggregate installation, concrete paving and boulevard grading for the subdivision. We used GPS machine controls to fast track this project for Genstar. Some of the major components of the project included:

  • 18,000t of granular material
  • 6,700m2 of slip-form and hand pour concrete paving

Being able to start this project after Taillieu Construction had completed all of the underground work and roadway excavation allowed us to maximize our resources and complete the project a full month ahead of schedule.

When you want it all, we do it all.

Our Story

Since 1992, Bayview has grown to meet the changing needs and opportunities in Manitoba's heavy construction industry.