2014 - Ness Avenue Concrete Reconstruction

Owner: City of Winnipeg | Value: 3.2 Million | Consultant: City of Winnipeg

The concrete reconstruction of Ness Avenue was tendered last winter with an accelerated completion clause as well as an aggressive 85 working days. Hard work and excellent planning from Bayview Construction and the City of Winnipeg, as well as multiple affected parties such as MB Hydro and many other private business resulted in maintaining traffic in both directions while completing the project 10 days ahead of schedule and within budget. Some of the major components of the project included:

  • 10,000m3 of excavation
  • 18,000t of granular material
  • 14,000m2 of slip-form and hand pour concrete paving
  • 3,900m2 of concrete sidewalk
  • 200m of 300mm new LDS installation

When you want it all, we do it all.